The efforts that went into the design of the
second Narrows Bridge were unique and had an important effect on the
design of suspension bridges and other similar structures that
followed. Approximately four years were spent in original research to
study aerodynamics and design features to achieve stability in the new
structure. The Consulting Board recognized that the question of
aerodynamic stability of suspension bridges would have to be resolved.
Although the development of aerodynamics in the 1940s was not unique as
applied to aircraft, there had been no previous scientific effort
devoted to the dynamic effect of winds passing over a bridge structure.
A special wind tunnel was constructed at the University of Washington
for testing three-dimensional bridge models; the first time such models
had ever been built. A 1:50 scale three-dimensional model of the
original bridge was built. The tests would prove that wind velocities
acting on models scaled to match the bridge's form and elastic
properties would create the same motions as those actually measured and
recorded in the field.
The first test proved the theory of
similitude between model and prototype with almost perfect accuracy
establishing confidence in tests on other designs. Many modifications
were necessary and the tests were spread over nearly four years during
the shortages of World War II, with its attendant handicaps, before the
desired degree of stability was found. Methods and devices necessary to
obtain the required stability were also determined. Tests were
performed under the general direction of Charles E. Andrew with the
approval of the Board of Consulting Engineers. Professor F.B.
Farquharson of the University of Washington directed the construction
of the wind tunnel and bridge models. Dr. Theodore von Karman
supervised testing of the models. Test results formed the basis for a
continuing study by a national committee comprised of many engineers in
the country interested in suspension bridges.
Because of the extreme shortage of steel and
wire during World War II, attempts were made to salvage all remaining
material from the first bridge. Ironically, it would have been more
economical for the state to drop the remaining portions of the
structure into the deep waters of the Puget Sound.
Designs for the new bridge were completed in
1947 and checked aerodynamically with the use of models. Contracts were
let for construction on March 31 and April 1, 1948. The primary
contractors for construction of the bridge were the Bethlehem Pacific
Coast Steel Corporation and John A. Roeblings Sons Company. Both of
these firms were notable for their innovative construction skills in
the fabrication and erection of steel bridges.
The Tacoma Narrows Bridge opened to traffic
on October 14, 1950; all components of the structure were finally in
place by November 1951. Construction was financed through a $14,000,000
bond issue. The bridge operated as a toll facility until the bonds were
retired, at which time the tolls were removed along with the toll plaza
and booths (although the toll houses remain off the south end of the
bridge). The toll for an automobile and driver was 50 cents. Each
additional passenger paid 10 cents.
At the time of completion, the Tacoma
Narrows Bridge included the third longest suspension span in the world.
As of 1991 it ranked as the fifth longest span in North America. This
bridge is of major significance because of its numerous unique design
features. It was the first time a research program was implemented to
investigate the aerodynamic effects of wind acting upon a bridge. In
designing this structure, bridge engineers first used wind tunnel tests
to determine the behavior and stability of a physical model of a
proposed bridge. The research and design provided significant
information to suspension bridge engineers nationwide and had an
important effect on all suspension bridge designs that followed. The
design incorporated unique features into the structure, such as the
open steel grid slots, the greater ratio of the depth of stiffening
truss to span length, the double lateral system, the hydraulic energy
absorbing and damping devices, and the record depth below water at
which pier construction occurred with the aid of submerged caissons.
Few bridges have received as much engineering significance in technical
publications or as much nation-wide attention and publicity, due
largely to the failure of the first Tacoma Narrows Bridge. The present
structure represents an extraordinary achievement in bridge design and
construction engineering. This effort produced a structure of
unprecedented function, stability, and virtually unequaled esthetic
attraction spanning one of the country's most challenging crossings. In
addition, the bridge established one of the most significant
transportation corridors in Washington State by connecting the mainland
with the Kitsap and Olympic peninsulas.